Daily Log Fields & Statuses

Every field on every section of the daily log, the option lists, and the status rules.

Lookup material for the daily log — every field on every section, the fixed option lists, and what each status lets you do.

FieldTypeNotes
DateCalendarDefaults to today. One log per project per date
Shiftday / night / swingDefaults to day. Labels the log; it does not split the day
ProjectRead-onlyName and code
LocationRead-onlyAppears once weather has been fetched with location permission

Weather

FieldNotes
Fetch WeatherFills the section from the site's conditions for that date
High Temp / Low TempNumbers
Unit°C or °F
ConditionsClear, Partly Cloudy, Cloudy, Rain, Heavy Rain, Snow, Fog, Windy
Humidity (%)Number
Precipitation (mm)Number
Wind Speed / Wind UnitNumber, with km/h or mph

An empty numeric field stays empty — it is not recorded as zero.

Manpower

One repeating row per company on site.

FieldNotes
CompanyWho supplied the labour
TradeWhat they were doing
HeadcountNumber of people
HoursHours worked
Notes (optional)Free text

Equipment

One repeating row per machine.

FieldNotes
TypeFor example, Crane
Description / IDPlant number or description
Hours used / Hours idleNumbers
StatusActive, Idle or Breakdown. Defaults to Active
Notes (optional)Free text

Work Performed

One repeating row per activity.

FieldNotes
Area / ZoneWhere the work happened
Trade (optional)Which trade did it
DescriptionWhat was built or done
% CompleteProgress on that activity

Delays

One repeating row per delay.

FieldNotes
CauseWeather, Material, Labor, Equipment, Design, Permit, Client, Subcontractor, Other
HoursHow long the delay ran
Responsible partyWho or what held it up
DescriptionWhat happened

Visitors

FieldNotes
Name, Company, PurposeWho came and why
Time in / Time outTimes
Badge # (optional)Visitor pass number

Safety

FieldNotes
Incident occurred?Toggle. When on, the register card shows a red incident warning
Incident DescriptionWhat happened
Near-miss CountNumber
Toolbox Talk TopicWhat was briefed
Talk AttendeesWho attended
PPE Compliance NotesFree text

Photos

FieldNotes
Upload PhotoOr click the Click to upload photos area when empty
CaptionWhat the photo shows
LocationFor example, "Zone B, Level 3"
SectionGeneral, Work, Safety or Delay

Notes

A single free-text box for anything the sections above do not cover. Text here counts towards the submit requirement.

Statuses

StatusRegister badgeEditableDeletableNext step
DraftDraftYesYes, by owner or project managerSubmit
SubmittedSubmitted, or Pending in the approval queueNoNoApprove or Return
ApprovedApprovedNoNoNone — approval is permanent

Rules Worth Knowing

  • Nothing is required while drafting. Completeness is only checked when you press Submit.
  • To submit, at least one of Manpower (company plus headcount), Work Performed (area plus description), Delays (description plus duration) or Notes must be filled in.
  • You cannot approve your own log. The rule is enforced on the server.
  • Only drafts can be edited or deleted, whatever your role.
  • Only approved logs are compiled into a client report.