Logging Deliveries

How to record a material delivery with the New Delivery dialog — all fields and options.

Quick Summary
  1. Click New Delivery in the toolbar
  2. Select Material — from inventory or approved submittals not yet in inventory
  3. Select Vendor — filtered to the material's approved suppliers
  4. Enter Quantity and Unit Cost (₹) — total cost previews automatically
  5. Set Delivery Date (defaults to today), optionally attach a DC Document, add Site Location and Remarks
  6. Click Add Delivery — delivery is logged and stock increases immediately

Full Guide

The New Delivery Dialog

New Delivery — all fields for recording a material arrival

When you click New Delivery, the dialog opens with these fields:

FieldRequiredDescription
MaterialYesDropdown with two sections: "In Inventory" and "Approved Materials (not in inventory)"
VendorYesDropdown filtered to the material's approved suppliers, as named on its submittal
QuantityYesAmount delivered in the material's unit (supports decimals, minimum 0.001)
Unit Cost (₹)YesCost per unit for this delivery (supports decimals)
Total Cost—Auto-calculated preview: quantity × unit cost (shown before saving)
Delivery DateNoCalendar picker, defaults to today
DC DocumentNoFile upload — accepts PDF, JPG, PNG, WebP
Site LocationNoWhere on-site the material was delivered (max 200 characters)
RemarksNoAdditional notes about the delivery (max 1,000 characters)

Material Selection — Two Sections

The material dropdown shows two groups:

In Inventory — Materials you're already tracking. Selecting one of these links the delivery to the existing inventory entry.

Approved Materials (not in inventory) — Submittals that have been approved but not yet added to your inventory. Selecting one of these:

  • Automatically creates an inventory entry for the material
  • Links the delivery to the new entry
  • The button text changes to Add to Inventory & Record Delivery

Shortcut

This is a convenient shortcut — instead of going to Inventory → Add to Inventory first, you can create the inventory entry and log the first delivery in a single step.

Vendor Filtering

When you select a material, the vendor dropdown filters automatically:

  • If the material has approved suppliers named on its submittal, only those vendors appear, and the field label reads "(filtered to approved)"
  • If none are named, every vendor you have not removed is shown — there is no separate signal for this beyond the missing label suffix
  • Removed vendors are never shown

Total Cost Preview

As you enter quantity and unit cost, the Total preview appears just below those two fields and updates as you type:

Total Cost = Quantity × Unit Cost

This helps you verify the numbers before saving.

Good Remarks Examples

Remarks add context that helps during audits and reviews:

  • "Scheduled delivery — PO #4523"
  • "Partial delivery — remaining 50 tonnes expected next week"
  • "Emergency order — rate premium approved by PM"
  • "Replacement for rejected batch — no additional cost"
  • "Delivered to secondary storage — Warehouse B"

What Happens After Saving

  • The delivery appears in the Deliveries table with a status badge
  • The quantity is added to your inventory stock immediately
  • The material's Total Cost in the Inventory tab increases by this delivery's cost
  • If you uploaded a DC document, it's linked to the delivery record

Questions

Does the unit cost I enter change the material's budget rate?

No. The unit cost stays on this delivery, and its total is added to the material's Total Cost. The budget rate stays what was set in Inventory (⋯ → Edit Budget), so you can compare what you paid with what you planned.

What budget does a material get when I add it from this dialog?

Picking one under Approved Materials (not in inventory) adds it with this delivery's unit cost as its budget rate, and no planned quantity. Set the real budget afterwards in the Inventory tab: ⋯ on its row → Edit Budget.

Can one delivery cover several materials?

No. Each delivery records one material. If a lorry brings several, log one delivery per material. You can attach the same challan to each of them.