Quality — Getting Started
Follow one problem from a failed inspection item to a closed NCR and a corrective action that has been checked.
This walk-through follows one problem from start to finish. A slab inspection fails on cover to reinforcement; you raise an NCR, decide what happens to the work, and deal with the cause.
Raise the NCR from the failed item
Open the inspection and find the failed item. Click Raise NCR beside it. The NCR starts with the item's details, and the line From … The link back to it stays on the record. tells you where it came from.
Check What is wrong, add the Requirement it missed and the Location if you know them, and note any Containment done so far. Pick the severity: Observation, Minor, Major or Critical. Click Raise NCR.
You can raise an NCR the same way from a defect's page or an audit finding, or by hand with Raise NCR on the Nonconformances register.
Record the containment
On the NCR's page, the Containment section asks What was done to contain it. Write what was done to stop the problem spreading, such as stopping the next pour, and save it. The page shows who recorded it and when.
Give the disposition
Someone whose role can approve NCRs chooses the Disposition: Rework, Repair, Use as is or Reject, then clicks Give disposition.
Repair and Use as is are recorded as a concession under the name of the person who gives them. If the client agreed, pick who gave consent in Client consent given by. If you can't approve NCRs, the section says Waiting on someone who can approve NCRs.
Decide on a corrective action
Before the NCR closes, the Corrective action section asks: Before this closes: could it happen again unless its cause is dealt with? Write Why, then click Corrective action needed or Not needed.
If it is needed, a corrective action opens, linked to the NCR. Open the corrective action takes you to it. Close the NCR from its Moves once the question is answered.
Work the corrective action
On the corrective action, write the Root cause, then Add step for each thing that has to be done: What has to be done, Who does it and Due. Each person clicks Mark done on their step.
When every step is done, use the All actions done move. The Effectiveness check opens 20 working days later.
Check that it worked
When the check is due, someone whose role can approve corrective actions answers Did the steps stop the problem coming back? with Effective or Not effective. Effective closes the corrective action. Not effective needs What you saw, sends it back to In progress and reopens its steps.
Next
- Nonconformances for every field and status
- Corrective actions for steps and the effectiveness check
- Quality audits to audit a process and build an evidence pack