Nonconformances (NCRs)

Raise an NCR by hand or from a defect, a failed inspection item or an audit finding, contain it, give its disposition, and close it.

A nonconformance (NCR) records work that did not meet its requirement, what was decided about it and what was done. Open Quality in the project menu and pick the NCRs tab.

The register

The register lists every NCR on the project, with All, Open and Ended views, a search box, and grouping by Status. Click a row to open the NCR.

The NCR register, grouped by status

Statuses

StatusMeaning
RaisedRecorded; waiting for its disposition
Disposition givenSomeone who can approve NCRs has decided what happens to the work
ClosedThe corrective-action question is answered and the NCR is closed
VoidCancelled, with a reason

Raising an NCR

Click Raise NCR on the register to record one by hand: What is wrong, an optional Requirement, Location and Containment done so far, a severity (Observation, Minor, Major or Critical) and an optional reference standard.

You can also raise an NCR where the problem was found: on a defect's page, beside a failed inspection item, or on an audit nonconformity. The form starts with that record's details, and the NCR keeps a link back to it. Once raised, the button becomes a link to the NCR, so the same item is not raised twice.

The NCR's Details show what is wrong, its severity, its Source (or Raised by hand), when and by whom it was raised, and the reference standard, requirement and location.

Containment and disposition

Containment. While the NCR is open, anyone whose role can update NCRs records What was done to contain it. The page shows who recorded it and when.

Disposition. Someone whose role can approve NCRs picks Rework, Repair, Use as is or Reject and clicks Give disposition. Repair and Use as is are recorded as a concession under that person's name, with an optional Client consent given by naming the member who gave the client's consent. Until then, the section reads Waiting on someone who can approve NCRs.

An NCR with its containment and a Repair disposition

On your company's standard NCR workflow, a rework or repair then opens a Verify the rework or repair sign-off step. It waits in My approvals for whoever the workflow names.

Corrective action and closing

Before an NCR closes, the Corrective action section asks whether it could happen again unless its cause is dealt with. Write Why and click Corrective action needed or Not needed. A corrective action that is needed opens linked to the NCR.

Close the NCR with Close in Moves once the question is answered. Someone whose role can approve NCRs can Void one raised by mistake, with a reason.

The bottom of the page shows the NCR's workflow: its Status, the Moves open to you (a move you can't make yet is greyed out with the reason), its Open steps and its Run history.