Reinspection

What happens when an inspection is sent back — what each party re-judges, the reinspection limit, and the issue resolution gates.

When the approver fails an item, the inspection goes back to the inspector for reinspection. How much each party must re-judge depends on your company's inspection workflow, which sets it separately for the inspector and for the approver. Previous verdicts, notes, and evidence are always kept for the audit trail and stay viewable in the comparison column — reinspection only decides what must be re-judged, it never deletes records.

When Reinspection Triggers

TriggerWhat Happens
The approver fails an itemOn a quality-critical checklist, the inspection goes straight back to the inspector to fix
Reinspect on a completed inspectionEvery completed inspection shows Reinspect. The project owner or anyone assigned to a party can use it to reopen the inspection for the inspector

The reinspection counter increments each time the inspection cycles back.

Re-Judging Modes

The inspection workflow's Reinspection and evidence rules set how much each party must re-judge on a reinspection: The inspector re-judges for the inspector, and The approver and reviewers re-judge for the approver. Nothing is deleted — items that must be re-judged are simply shown as pending until the party records a fresh verdict; previous records stay viewable in the comparison column.

ModeEffectWhen to Use
Re-do failed onlyThe party only re-judges the items that were sent back (the ones they failed). Passed and N/A items carry forward.The default: only the failed items are re-checked, which saves time on large checklists
Re-do everythingThe party re-judges every item from scratch (shown as pending). Previous records kept.When a repair can disturb the items around it and you want the inspector to re-evaluate everything without bias from prior results
Carry everything forwardNothing needs re-judging — previous verdicts carry forward. The party can still update any item.When you want to keep prior results and selectively update — useful for minor corrections

Default Configuration

PartyDefault Mode
The inspector (the Performer slot)Re-do failed only
The approver (the last slot, on quality-critical work)Re-do failed only

Set by your workflow

By default a reinspection re-does only the items that were sent back; the banner on the inspection lists them. These are the rules on a new inspection. Admins change them (for example to Re-do everything for the inspector) in the inspection workflow, under Admin → Workflows, and a project can have its own version. An inspection keeps the rules of the workflow version it started on, so one already under way can differ.

Reinspection Limits

RuleOn a new inspectionEffect
Reinspection limitNoneWhen the inspection's workflow has a limit, the approver's fail is refused once it is reached, with a message naming the limit.

If the limit is reached, the inspection stays in its current state and cannot be cycled back. This prevents endless inspection loops on problematic items.

Issue Resolution Gate

The flow with issue resolution:

  1. An item fails → quality issues raised for failed items
  2. Whoever was picked to fix each one fixes the defect → marks the issue as Fixed
  3. ALL sibling issues must be Fixed
  4. Only then can the inspector submit the reinspection
  5. On a successful reinspection submit → Fixed issues auto-close

A passing submission also closes every linked issue marked Fixed, even when the inspection was never sent back — for example a routine inspection where you raised an issue during the run, had it fixed, and then passed the item.

Issue Rules During Reinspection

  • Only an issue's assignee fixes it. The inspector fixes an issue only when they are its assignee, and cannot close it directly
  • Only the Performer, when it is their turn on the inspection, can re-inspect or Reject Fix. A reviewer or approver judges the reinspection afterwards; while the inspection is with them they send it back instead of rejecting the fix. If they've left the project, the slot can be handed to someone else (Reassigning a party slot)
  • ALL sibling issues (from the same inspection) must be Fixed before any single issue can close
  • Auto-close fires when the inspector submits the reinspection AND all issues are Fixed

The Reinspection Cycle

text

An inspection started on an earlier workflow version cycles through every party again after a reinspection — Performer, then each Checker, then the Approver — and any of them failing an item sends it back to the Performer (Who Signs an Inspection).

Next Steps

Questions

What do I do when the reinspection limit is reached?

The approver's fail can't be submitted, and the inspection stays where it is. The limit belongs to the workflow version the inspection started on, so it can't be raised for that inspection. If more rounds are needed, cancel it and start a new one.

Why were issues created when nobody picked Raise an issue?

The inspection's workflow raises an issue when an item fails. When an inspection is sent back, an issue is raised for every failed item, whatever action its fail page had.

Do Fixed issues stop my reinspection from being submitted?

No. Only a linked issue that's still Open or In Progress blocks the submit. When the inspection passes, every linked issue marked Fixed closes on its own, even on a routine inspection that was never sent back.